There has
been a lot going on at the Costain/Tesco site in 2009, most of it
largely unnoticed by the local population. One important activity
has been the replacement of the tunnel segments destroyed during or
immediately after the collapse on June 30, 2005. Even this is not
very obvious unless you look over the parapet of Marsham Lane bridge
although the sight of the blue framework of the crane visible over
the public car park fence could hardly be ignored.
This page
is an account of the final part of this replacement task, made possible
by a lot of preliminary ground work and some research and experiment
into the design of the segments. 63 segments were placed, 2 of
them half-segments to the original design to square off the ends of the
original tunnels, 2 half-segments to start and end the sequence of
new-design segments, and 59 full size new segments. The
new-design segments are not obviously different from the original ones
but they do have a slightly different profile and the mating of the
north and south segments at the crown is different.
I have
used the word "completion" but that only means that there is now
one tunnel instead of the two we have had since 2005. There is a
brief account of "what next" at the end of the page.
Click on a
thumbnail to see a larger image. You can go the TescoTunnel
home page here.
Installing the replacement tunnel segments.
A 250t crawler crane was brought to and assembled at the Costain
site. The segments weigh around 22 tonnes each, but they need to
be lifted at a considerable radius. Date February 14.

A very large platform was built for the crawler crane, together with a
wide access route. Preparations included stabilising the ground
underneath, boring some deep piles and safety fences round
everything. The crane placement and preparation work are quite
different from those employed by the original contractor. You can
see both the earlier cranes on other pages of this website. Date
February 20.
The first task undertaken by the crane was
to assist the building of this temporary gantry. All this work
was, of course, done at night during a Possession. When complete,
as shown in the next picture, the gantry was used to support the
first segment being placed as there was no opposing segment for it to
be supported by. Once segments were in place, the crane could no
longer reach the gantry which had to be dismantled from track level
and taken out through the tunnel.
The train, 165018, is heading west into the western part of the
tunnel. The eastern, and shorter, part is in the foreground.
In a few more days, trains will be invisible as they were in
2005. Date February 23.
With the additional structure on
the top, the gantry is ready for
use. Date February 27.
The first new segments have been
placed. The temporary supporting gantry is now
redundant. This is where your scribe confesses that he fully
intended to get out of bed in the early hours to take some nighttime
action photos but regrettably his willpower proved inadequate to the
task. Date March 2.
The
base and the channel for the segments survived the 2005 collapse and
are in
quite good order. After all the rubble, fill material and other
covering was removed only a small amount of remedial work was needed to
make them fit for use now. The foot of each segment is
retained in position by wooden blocks and wedges which are later
replaced by grouting the gap.
Another segment is waiting beside the
crane for lifting into place at the next Possession. Note that it
is resting on its side, not on its ends - it is said that the segments
are so flexible that if they were to stand for any length of time on
their ends, they would become distorted and would take up an incorrect
profile. Date March 4.
The detail of how the north-side segments
fit into the south-side segments at the tunnel crown is slightly
different in the new design. Date March 4.
Segments queue for placement.
Date March 4.
North side segments are firmly anchored
into their channel. On the right is the lower part of the
platform being used by the crane. Two things are worth noting
here. Along the right-hand edge of the tunnel bases a rail system
will be fixed for a gantry that will straddle the tunnel segments for
the work to be done over the top and down the sides of these segments.
The other thing to note is that the entire tunnel length from here to
Packhorse Road bridge to the west, on both south and north sides, will
have to be excavated to the level you see here. Whilst a lot of
preparatory work has been done, it is not very photo-worthy, but I hope
to record some of the action later. Date March 5.
The temporary gantry is no longer in
use but has not yet been removed. The space for the old-type half
segment shows daylight. Date March 5
Here is the
space from a different angle. The stainless steel face to the
opposing segment shows clearly from here. Date March 5.
The next three pictures are of a delivery of yet another segment. Date March 5.
The streak of sunshine on to the track
through the tunnel gap will be extinguished permanently in a few
days. I hope the passengers in Chiltern 168002 enjoyed it.
Date March 6.
Approaching the halfway mark in segment
placement. Date March 11.
More segments in place and many
grouted.
Date March 13
Just a small gap left to fill. Date
March 19
The view along the north side. Also
seen is the crane platform at the right, built up in layers on earlier
layers. Date March 20.
Meanwhile the team on the south side is
mixing and placing grout. Date March 20.
Segment placement is almost complete,
there being just one half segment to go in at the other end on the left
on this picture - the gap is protected by safety fencing. In the
foreground, looking west, it is possible to see the slight difference
in profile where the new segments meet the old. The stitching
beams on the new segments do not stand so high so that the top of the
concrete is at the same level as on the old segments. Date April
3.
The slight profile change shows here
too. On the right is the base of the crane platform. The
ground it stands on is at approximately the level created during the
recovery work after the collapse, but hugely reinforced in a number of
ways. Date April 3.
Looking east towards Marsham Lane Bridge,
the almost completed new work completes the link from Packhorse Road
bridge to just short of Marsham Lane bridge. Date April 8.
Overview from the north side of the linked
tunnels. Date April 8.
The north side complete. Date April
8.
Just the last half-segment waits to be
lifted
and fitted in the gap, which we have seen in earlier pictures,
between the old western tunnel and the new segments.
Date April 8.

Finally the last segment is in place so the south side is also
complete. Date Apr 17.
What next? The old and new tunnel segments seen in this and
other pages will be used as formers for the placement of a reinforced
concrete outer casing. There is a small diagram of the general
idea at http://www.tescogerrardscross.co.uk/newplans.html but
unfortunately the larger version that was available seems to have been
removed. The new casing will be the load bearing structure, not
the precast concrete segments.
You
can go
the
TescoTunnel home page here.
Pictures
and text © Guy Gorton 2009
Updated 8th June 2009